Cutting of pavement: 2026 Alberta unit price

What Alberta paid for cutting of pavement on provincial highway contracts in 2026, from 27 contracts, and how the average has moved since 2024.

Sheet D-610Checked 2026-10-252 min read1 source

$8.43/mAlberta 2026 average, item X5101
−29%Change from the 2025 average of $11.89
27Contracts behind the 2026 average

STA 0+120What cutting of pavement covers

Pavement cutting is saw-cutting an existing asphalt or concrete surface to a clean line, usually before a trench, patch or removal so that the edge does not ravel. It is priced per metre of cut and is one of the more frequently tendered items on urban and intersection work.

STA 0+2402026 price and three-year history

In 2026 the provincial average for Cutting of Pavement (item X510) was $8.43 per m1, the average of the three lowest bids on 27 contracts tendered May 1, 2025 to June 24, 2026. That is down 29% on the 2025 average of $11.89 (31 contracts) and down 19% on 2024's $10.40 (29 contracts).

Cutting of pavement: three-year history1
ItemUnit2026 avgContracts2025 avg2024 avgvs 2025
Cutting of PavementItem X510m$8.4327$11.8931 contracts$10.4029 contracts−29%

STA 0+360How the price varies across Alberta

Alberta reports regional averages for only a minority of items, and none for cutting of pavement. The provincial average above is the only published figure, so a region with long hauls or little competition will usually price above it.

STA 0+480What moves the price

Pavement thickness, whether the surface is asphalt or concrete, the length of cut on each setup, access and traffic control, and how often the work is interrupted change the rate. Short cuts spread the crew's setup time over fewer metres.

STA 0+600Using the number in a budget

These are benchmarks, not quotes. Each figure is the average of the three lowest bids on Alberta provincial highway contracts, at highway quantities: contracts in this sample averaged about 5,200 m of this item. A small private job pays more per unit because mobilization, minimum charges and disposal are spread over less work.

Arithmetic only: 500 m at the provincial average is $4,215, before any small-job premium. Use the number to sanity-check a unit rate in a bid or to see which way a price has moved, then ask for a quote that matches your quantities, access and timing.

STA 0+720Related prices, guides and tools

Questions people ask

How much does cutting of pavement cost in Alberta?

On Alberta provincial highway tenders in 2026, Cutting of Pavement (item X510) averaged $8.43 per m1, the average of the three lowest bids across 27 contracts. It is a highway-scale benchmark, not a quote for a particular job.

Has the price of cutting of pavement gone up?

The 2026 average of $8.43 per m is down 29% on the 2025 average of $11.89 and down 19% on 2024's $10.40. Annual averages move with the mix of contracts tendered, so a change in the average is not the same as a change in the cost of the work.

Can I use this price for a small job, or outside Alberta?

Use it as a reference point, not a price. The average reflects highway contracts that averaged about 5,200 m of this item, so a smaller job usually costs more per unit, and no other province publishes a comparable average for this item. For your own job, send the scope, quantities and location on the project brief and we reply by email.

Sources

  1. Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026