Curb and gutter: 2026 Alberta unit price
What Alberta paid for curb and gutter on provincial highway contracts in 2026, from 5 contracts, and how the average has moved since 2024.
STA 0+120What curb and gutter covers
Curb and gutter is the formed concrete edge and drainage channel along a street. Alberta prices curb and gutter (X325), curb alone (X320) and a monolithic sidewalk, curb and gutter section (X310) per metre.
All three rest on only a handful of contracts, so treat them as a rough guide to the scale of the cost and not a benchmark.
STA 0+2402026 prices and three-year history
In 2026 the provincial average for Curb and Gutter (item X325) was $183.00 per m1, the average of the three lowest bids on 5 contracts tendered May 1, 2025 to June 24, 2026. That is down 23% on the 2025 average of $238.70 (8 contracts) and up 17% on 2024's $156.15 (10 contracts).
| Item | Unit | 2026 avg | Contracts | 2025 avg | 2024 avg | vs 2025 |
|---|---|---|---|---|---|---|
| Curb and GutterItem X325 | m | $183.00 | 5 | $238.708 contracts | $156.1510 contracts | −23% |
| Concrete CurbItem X320 | m | $175.24 | 3 | $188.014 contracts | — | −7% |
| Monolithic Sidewalk, Curb and GutterItem X310 | m | $416.14 | 3 | $450.442 contracts | $346.213 contracts | −8% |
Read the swings with care. Item X325 moved by a factor of 1.5 between its highest and lowest annual average. Averages like these usually reflect which contracts happened to be tendered in a given year more than a change in the cost of the work.
STA 0+360How the price varies across Alberta
Alberta publishes regional averages for some items. For item X325, Central averaged $208.58 and Peace $169.53, which is 23% higher. Regional gaps like this come from haul distance, local competition and the mix of work tendered in each region.
| Region | Avg per m | Contracts |
|---|---|---|
| Southern region | $180.00 | 1 |
| Central region | $208.58 | 3 |
| Peace region | $169.53 | 1 |
| Province | $183.00 | 5 |
STA 0+480What moves the price
Form type (slip-form machines are faster on long straight runs, hand forming costs more around curves and corners), concrete price, subgrade and base preparation, finishing and curing, and traffic control set the rate. Short runs and many intersections push the per-metre cost up.
STA 0+600Using the number in a budget
These are benchmarks, not quotes. Each figure is the average of the three lowest bids on Alberta provincial highway contracts, at highway quantities: contracts in this sample averaged about 1,500 m of this item. A small private job pays more per unit because mobilization, minimum charges and disposal are spread over less work.
Arithmetic only: 200 m at the provincial average is $36,600, before any small-job premium. Use the number to sanity-check a unit rate in a bid or to see which way a price has moved, then ask for a quote that matches your quantities, access and timing.
STA 0+720Related prices, guides and tools
Questions people ask
How much does curb and gutter cost in Alberta?
On Alberta provincial highway tenders in 2026, Curb and Gutter (item X325) averaged $183.00 per m1, the average of the three lowest bids across 5 contracts. It is a highway-scale benchmark, not a quote for a particular job.
Has the price of curb and gutter gone up?
The 2026 average of $183.00 per m is down 23% on the 2025 average of $238.70 and up 17% on 2024's $156.15. Annual averages move with the mix of contracts tendered, so a change in the average is not the same as a change in the cost of the work.
Can I use this price for a small job, or outside Alberta?
Use it as a reference point, not a price. The average reflects highway contracts that averaged about 1,500 m of this item, so a smaller job usually costs more per unit, and no other province publishes a comparable average for this item. For your own job, send the scope, quantities and location on the project brief and we reply by email.
Why does Alberta list curb and gutter under several item codes?
Each code is a separate tender item with its own specification, and the workbook gives no description beyond the item name. Cite prices by code, and read the contract documents to see what each code includes.
Sources
- Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026