Guide · Sheet G-401

Call before you dig: how to get utility locates in Canada

Before any bucket touches the ground, the buried lines under it need to be found and marked. Every province runs a free one-call service to do it; the notice period and the legal backing behind it are not the same everywhere.

Sheet G-401Checked 2026-09-246 min read10 sources

3 to 5 daysFull working days’ notice Utility Safety Partners asks for in Alberta before a planned dig2
5 business daysStatutory deadline for an Ontario One Call member to mark or clear a standard locate request1
2 hoursOntario’s statutory response window for an emergency locate request1

"Call before you dig" is not a slogan, it is a legal notification system. An excavator paints the proposed work area white, submits a request to the province's one-call centre, and the owners of buried gas, electrical, telecom and water lines have to come out and mark their own facilities before work starts. The mechanics, the notice period and how much of it is actually written into law differ by province. This guide lines them up so you can plan a mobilization date around the real notice period, not a guess.

The same request also protects the excavator. A locate ticket is the paper trail that shows due diligence was done before ground was disturbed, which matters if a strike happens anyway on a line that was mismarked, unmarked, or outside the facility owner's own records.

STA 0+120The one-call centre in every province

Each of these is a free service. None of them charge an excavator to submit a request or a facility owner to respond to one1.

One-call centres and notice periods by province
ProvinceOne-call centreMinimum noticeContact
AlbertaUtility Safety Partners (Click Before You Dig)3 to 5 full working days; longer May–September2utilitysafety.ca or 1-800-242-34472
British ColumbiaBC 1 Call3 business days3bc1c.ca or 1-800-474-68863
SaskatchewanSask 1st Call3 full business days routine; 10 business days for planning and design tickets4sask1stcall.com or 1-866-828-48884
ManitobaClick Before You Dig Manitoba3 full working days5clickbeforeyoudigmb.com or 1-800-940-34475
OntarioOntario One Call5 business days (statutory)1ontarioonecall.ca1
Quebec, New Brunswick, Nova Scotia, PEI, Newfoundland and LabradorInfo-Excavation3 business days6info-ex.com or 1-800-663-92286

Sask 1st Call's locate marks are valid for 30 calendar days from the ticket4, and Utility Safety Partners recommends building in more lead time between May and September, when request volume peaks2.

STA 0+240Ontario runs on a statute, not just a member agreement

Ontario is the one province where the notification system is written directly into legislation, the Ontario Underground Infrastructure Notification System Act, 2012. That changes what an excavator can rely on:

  • Standard request: a member receiving a locate request must mark its infrastructure, or confirm none is affected, within 5 business days of notification1.
  • Emergency request: a member must have someone on site, or provide a no-conflict statement, within 2 hours1.
  • Earliest submission: an excavator cannot submit a standard request more than 30 days before the dig is expected to start, and cannot start until locates are provided1.
  • No fee: members cannot charge for responding to a locate request1.

Coming November 1, 2026 (announced)

Ontario One Call has announced a new "Continuation to Dig After Expiry of Validity Period" regulation taking effect November 1, 2026. Once in force, eligible projects would be able to keep digging without a fresh locate for up to 180 days from the last locate document7. This is an announced change, not yet the current rule; confirm the regulation is in force and read its conditions before relying on it.

STA 0+360Federally regulated pipelines

Interprovincial and international pipelines fall under the Canadian Energy Regulator, not the provincial one-call system alone. Anyone planning ground disturbance within the prescribed area, or work that crosses, sits on, or runs along or under a federally regulated pipeline, must submit a locate request through the one-call centre at least 3 working days before starting8. The prescribed area is a strip of land 30 m on each side of the pipeline centreline8. This is separate from, and in addition to, the provincial one-call request: a project that crosses a federally regulated line typically needs both the provincial ticket and direct contact with the pipeline operator listed for that segment. See trench safety and shoring for how provincial excavation rules layer additional proximity requirements on top of this, such as Alberta's 600 mm hand-digging zone around a marked line.

STA 0+480What the paint and flags mean

Canada uses a common colour code for utility locate marking, published by the Canadian Common Ground Alliance and mirrored in a 2022 colour code sheet from Utility Safety Partners in Alberta9:

Utility locate marking colour code
ColourMeaning
WhiteProposed excavation10
PinkTemporary survey markings10
RedElectric power lines, cables, conduit and lighting cables10
OrangeCommunication, alarm or signal lines, cables or conduit10
YellowGas, oil, steam, petroleum or gaseous materials10
BluePotable water10
GreenSewers and drain lines10
PurpleReclaimed water, irrigation and slurry lines10

White paint or flags always come first: the excavator marks the proposed work area white before submitting the request, so the facility owners know exactly where to check10. Paint fades and flags get knocked over on an active site, especially through wet weather or heavy equipment traffic, so it is worth photographing the marks when they go in and re-requesting a locate rather than relying on memory if work is delayed past the marks' stated validity period.

STA 0+600The request-to-dig sequence

The mechanics are consistent across every province, even where the notice period differs:

  1. Mark the proposed excavation area white on the ground.
  2. Submit a locate request online or by phone to the province's one-call centre, with the address, work description and start date.
  3. The centre notifies its member facility owners, who each have their own crews mark their own lines within the notice period.
  4. Wait for the notice period to run before starting, and confirm every affected owner has responded, not just some of them.
  5. Expose lines by hand or hydrovac within the proximity zone set by the provincial excavation regulation before using mechanical equipment near a marked line. See hydrovac excavation and trench safety and shoring.
  6. If marks are missing, unclear or expire before the dig starts, request a re-locate rather than guessing.

This sequence is also the first step in the earthworks sequence described in earthworks and excavation and in the site servicing process. Skipping a step is where most utility strikes come from: a hit on a live gas or electrical line is not just a schedule problem, it is an incident report, a repair bill charged back to the excavator, and in a serious case a stop-work order until the cause is reviewed. The notice periods above exist because the facility owner, not the excavator, decides how quickly its own crews can get a locator to the site.

STA 0+720What locates do not cover

A one-call centre notifies its own member facility owners. It does not mark lines a property owner installed privately, such as a service run to a detached garage, an irrigation line, or a private well line, and it does not replace the provincial excavation rules covered in trench safety and shoring. In Quebec and the Atlantic provinces, Info-Excavation's own guidance describes placing a request as strongly recommended rather than mandatory, though the provincial occupational health and safety rules separately require an employer to locate services before digging6. A locate ticket is also not a survey: it tells you a facility owner marked an approximate corridor, not the exact depth or whether other buried objects are present, so hand exposure near a mark is still the safest way to confirm what is actually there before a machine gets close.

Questions people ask

Is calling before you dig free in Canada?

Yes. Every one-call centre listed above is a free service for the excavator, and in Ontario members are legally barred from charging a fee to respond to a locate request1.

How many days notice do I need before I can start digging?

It depends on the province: 3 business days in British Columbia, Saskatchewan and through Info-Excavation in Quebec and the Atlantic provinces3, 3 full working days in Manitoba5, 3 to 5 full working days in Alberta2, and a statutory 5 business days in Ontario1.

What do the different paint colours mean?

White marks the proposed excavation, red is electrical, yellow is gas or other petroleum lines, orange is communications, blue is potable water, green is sewer or drain, purple is irrigation or reclaimed water, and pink is temporary survey markings10101010.

What is changing with Ontario locates on November 1, 2026?

Ontario One Call has announced a regulation letting eligible projects continue digging for up to 180 days after their last locate document without a fresh request7. It has not taken effect yet; confirm it is in force before relying on it.

Do locate requests cover pipelines?

Federally regulated pipelines have their own notice rule: a locate request through the one-call centre at least 3 working days before work, for any ground disturbance within 30 m of the pipeline centreline88. Provincial rules add further proximity requirements once the line is marked.

Is a locate request legally mandatory everywhere?

The one-call centre itself may describe a request as strongly recommended rather than mandatory, as Info-Excavation does for Quebec and the Atlantic provinces6. Separately, most provincial occupational health and safety rules require an employer to locate underground services before excavating, regardless of whether a one-call request was filed.

Sources

  1. Ontario Underground Infrastructure Notification System Act, 2012, S.O. 2012, c. 4Government of Ontario (e-Laws) · current to 2026-09-21
  2. Notification ProcessUtility Safety Partners · retrieved 2026-09-24
  3. Click or call before you dig (WorkSafeBC toolbox meeting guide) and BC 1 Call support pagesBC 1 Call / WorkSafeBC · retrieved 2026-09-24 (BC 1 Call support page not directly fetchable; from search excerpts)
  4. FAQs - Sask 1st CallSask 1st Call · retrieved 2026-09-24
  5. Contractors - Click Before You Dig ManitobaClick Before You Dig Manitoba · retrieved 2026-09-24
  6. FAQ - Frequently Asked Questions | Info-exInfo-Excavation · retrieved 2026-09-24
  7. Ontario One Call Updates: New Regulation, System Improvements and EventsOntario One Call · effective 2026-11-01 (announced; regulation number not confirmed)
  8. Canadian Energy Regulator Pipeline Damage Prevention Regulations - Authorizations (SOR/2016-124)Justice Laws Website (Government of Canada) · retrieved 2026-09-24
  9. Colour Code ExplanationUtility Safety Partners · 2022 (from search excerpt)
  10. CCGA Best Practices Version 3.0 (October 2018), uniform colour code (page 41)Canadian Common Ground Alliance · Best Practices v3.0, Oct 2018 (a v5.0 was reported released in 2024; not checked)