CivilConstruction.ca
Project brief
Concrete pouring from a pump hose into a grid of reinforcing steel inside timber formwork

Guide · Sheet G-405

Prompt payment rules for construction in Canada

Prompt payment legislation replaces "net 60, maybe" with a statutory clock: a deadline to pay a proper invoice, a deadline to dispute it, and a fast adjudication process instead of a lawsuit. It is now in force in several provinces and federally, and explicitly not yet in force in two others.

Sheet G-405Checked 2026-09-245 min read10 sources

28 daysDeadline for an owner to pay a proper invoice under Ontario’s Construction Act, matched by Alberta, Saskatchewan, Manitoba and the federal regime1
7 daysDeadline for a contractor to pay a subcontractor after the contractor itself is paid, under Ontario’s Construction Act1
14 daysDeadline to issue a notice of non-payment, inside Alberta’s 28-day payment window, under prompt payment rules in force since 20222

Prompt payment legislation runs on a chain of deadlines, not general expectations. An owner who receives a proper invoice has a fixed number of days to pay it or formally dispute it; a contractor who gets paid has a fixed number of days to pay its subcontractors; and a dispute goes to a fast adjudicator instead of sitting in a queue for court. The days are similar from province to province, but two provinces have passed the legislation without bringing it into force, and that distinction is easy to get wrong.

None of this replaces the holdback a payer is separately required to retain: see construction holdbacks for the percentage and release timing, since a contractor can be paid promptly on the 90% progress portion of an invoice while the remaining 10% stays subject to a completely different release date.

STA 0+120How the payment clock runs

Where prompt payment legislation is in force, it follows the same basic shape everywhere it exists:

  1. The contractor (or subcontractor) submits a proper invoice.
  2. The owner has a fixed number of days to pay it in full — 28 days under Ontario's Construction Act1, Alberta's Prompt Payment and Construction Lien Act2, Saskatchewan's Builders' Lien Act3, Manitoba's Builders' Liens Act4 and the federal real property regime5.
  3. If the owner disputes the invoice, it must issue a notice of non-payment within a shorter window — 14 days in Ontario1, Alberta2, Saskatchewan3 and Manitoba4, 21 days federally5.
  4. Once the contractor is paid, it has to pay its subcontractors within a further short window — 7 days in Ontario1, Alberta2, Saskatchewan3 and Manitoba4.
  5. An unpaid party can refer the dispute to adjudication rather than waiting for a civil claim to work through the courts.

STA 0+240Status and timelines by jurisdiction

Prompt payment status and core timelines
JurisdictionStatusOwner pays withinContractor pays sub withinAdjudication
AlbertaIn force since August 29, 2022628 days27 days2ARCANA and ADACC nominating authorities6
OntarioIn force28 days17 days1Available under s. 13.5 of the Construction Act1
SaskatchewanIn force since March 1, 2022728 days37 days3Saskatchewan Construction Dispute Resolution Office7
ManitobaIn force (2025 per secondary sources)428 days47 days, full amount within 35 days4Adjudication under Part added by S.M. 2023, c. 304
British ColumbiaNOT in force; Royal Assent November 27, 2025828 days once in force87 days once in force8Adjudication authority not yet selected8
Nova ScotiaNOT in force; regulations still being developed9Not yet in forceNot yet in forceNot yet in force
Federal (real property)In force since December 9, 2023528 days535 days from Crown receipt of invoice; sub-subcontractors within 42 days5Adjudicator's determination under s. 16(1)10

Quebec and the remaining Atlantic provinces are not included above because a confirmed prompt payment timeline was not verified for them in the current research.

STA 0+360British Columbia and Nova Scotia: passed, not active

This is the distinction most worth getting right. British Columbia's Construction Prompt Payment Act received Royal Assent on November 27, 2025 but is not yet in force; it comes into effect on a future date set by regulation, and once it does, the 28-day owner-payment clock, 7-day subcontractor clock and 14-day dispute notice apply, with the adjudication authority still to be named8. Nova Scotia passed its own prompt payment and adjudication amendments through Bill 119 (2019) and Bill 211 (2022), but the government has stated it is still developing supporting regulations, and no prompt payment timelines currently sit in the consolidated Act9. In both provinces, a contractor working today is still on the older builders lien framework for payment timing, not the new one.

STA 0+480Federal real property contracts

The Federal Prompt Payment for Construction Work Act covers federal real property projects. The Crown or its service provider must pay a proper invoice no later than the 28th day after receiving it, with a notice of non-payment due no later than the 21st day5. A contractor paid by the Crown must pay each subcontractor no later than the 35th day after the Crown received the invoice, with its own notice of non-payment due by the 28th day; a subcontractor paid that way must in turn pay its own subcontractors no later than the 42nd day5. Interest on a late amount is calculated at the average bank rate plus 3% simple interest per year, and Saturdays, statutory holidays and the period from December 24 to January 1 are excluded from every day-count10. Alberta's provincial prompt payment regime, in force since August 29, 2022, specifically exempts Government of Alberta project contracts, which fall under the Public Works Act instead6 — a reminder to check which regime actually governs a given public contract rather than assuming.

STA 0+600What counts as a proper invoice

The clock does not start on any piece of paper called an invoice; it starts on a "proper invoice" as each act defines it, which generally means one that identifies the contractor, describes the work or materials and the period covered, states the amount claimed and how it was calculated, and is submitted in a form the contract or the act allows. An invoice missing required backup, sent to the wrong party, or submitted before the work it bills for was actually done, is not a proper invoice yet, and a dispute over whether the clock has even started is one of the more common early flashpoints in a prompt payment claim. Contractors working on a jurisdiction's prompt payment regime for the first time should confirm exactly what their contract and the applicable act require an invoice to include before assuming a submission date is also the clock-start date.

STA 0+720What adjudication actually does

Adjudication is not arbitration and it is not a lawsuit. It is a fast, interim determination by a qualified adjudicator, meant to keep cash moving on a live project rather than freezing payment for months while a full dispute works through the courts. A losing party can generally still pursue the underlying dispute later through litigation or arbitration; adjudication settles who pays what right now, not who was ultimately right. That distinction is the point of the whole system: a subcontractor with cash tied up in a disputed invoice does not have to choose between walking off a job and funding months of litigation just to keep working. Each jurisdiction designates its own nominating authority to run the process and maintain a roster of qualified adjudicators — Alberta, whose regime took effect August 29, 2022, uses ARCANA and ADACC6; Saskatchewan, in force since March 1, 2022, uses the Saskatchewan Construction Dispute Resolution Office7 — and a party has to refer a dispute to that authority to get an adjudicator assigned.

Legal information, not legal advice

Prompt payment deadlines, exemptions and adjudication procedures are detailed and change with amendments. This is a planning summary, not a substitute for the current statute and legal advice on a specific payment dispute.

Questions people ask

Is prompt payment legislation in force in British Columbia?

No. BC’s Construction Prompt Payment Act received Royal Assent on November 27, 2025 but takes effect on a future date set by regulation; it is not yet in force and the adjudication authority has not been named8.

Is prompt payment legislation in force in Nova Scotia?

No. Nova Scotia passed amendments in 2019 and 2022 but the government says it is still developing the supporting regulations, so no prompt payment timelines are currently in force9.

How many days does an owner have to pay an invoice?

28 days is the standard across the jurisdictions where prompt payment is in force: Ontario1, Alberta2, Saskatchewan3, Manitoba4 and federally5.

How is a dispute over an invoice resolved?

Through adjudication: a fast, interim decision by a qualified adjudicator assigned by the jurisdiction’s nominating authority, rather than a full court claim. It resolves who gets paid now, not the final legal outcome of the underlying dispute.

Do Government of Alberta contracts follow the provincial prompt payment timelines?

No. Even though Alberta’s regime has applied since 2022, Government of Alberta project contracts fall under the Public Works Act and are exempt from the provincial prompt payment timelines6.

What is the interest rate on a late payment under the federal rules?

The average bank rate plus 3% simple interest per year, with Saturdays, statutory holidays and December 24 to January 1 excluded from the day-counts10.

Sources

  1. Construction Act, R.S.O. 1990, c. C.30Government of Ontario (e-Laws) · consolidation current to e-Laws currency date 2026-09-21
  2. Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 (office consolidation current as of April 1, 2025)Alberta King's Printer · current as of 2025-04-01
  3. The Builders' Lien Act, SS 1984-85-86, c B-7.1 (consolidation incl. 2024, c 4)Government of Saskatchewan · consolidation incl. 2024, c 4
  4. The Builders' Liens Act, C.C.S.M. c. B91Government of Manitoba (Manitoba Laws) · retrieved 2026-09-24; in force April 1, 2025 per secondary sources
  5. Federal Prompt Payment for Construction Work Act, S.C. 2019, c. 29, s. 387Justice Laws Website (Government of Canada) · Act current to 2026-09-03; in force 2023-12-09
  6. Prompt payment rules for construction industryGovernment of Alberta · retrieved 2026-09-24
  7. Legislation to protect contractors takes effect todayGovernment of Saskatchewan · 2022-03-01
  8. Prompt payment legislationGovernment of British Columbia · page updated 2026-08-20
  9. Prompt payment and dispute resolution for the construction industry: engagementGovernment of Nova Scotia · engagement page (survey closed 2023-04-10); status as consolidated 2026-09-24
  10. Federal Prompt Payment for Construction Work Regulations (Criteria, Time Limits, Interest and Circumstances), SOR/2023-269Justice Laws Website (Government of Canada) · in force 2023-12-09