CivilConstruction.ca
Project brief
Aerial view of a highway being cut through pink granite, with an excavator loading a haul truck and lakes beyond

Calculator · Sheet T-208

Haul truck cycle time calculator

Load, haul, dump and return: cycle time, trips per hour, and how many trucks keep the excavator busy.

Haul truck cycle time · Sheet T-208Metric
km
km/h
km/h
min
min
m³ loose
m³/h loose
min per hour
Working minutes per hour after delays.
Estimates only. Check quantities against the drawings and your supplier before ordering.

STA 0+120How it works

Cycle time = load + haul (distance ÷ loaded speed) + dump and spot + return (distance ÷ empty speed). Trips per truck per hour = efficiency minutes ÷ cycle time. Trucks required = excavator production ÷ (trips per hour × capacity), rounded up. Actual production is the lower of the loader and the fleet.

STA 0+240Assumptions and sources

All inputs are yours: speeds depend on haul road grade, surface and rolling resistance; capacity depends on the truck and material. Check legal payloads: in Alberta, for example, a tandem axle group with eight or more tires is limited to 17,000 kg1, and spring road bans reduce it further.

Questions people ask

How do you calculate truck cycle time?

Add load time, haul time (distance ÷ loaded speed), dump and spot time, and return time (distance ÷ empty speed).

How many trucks do I need for an excavator?

Divide the excavator’s hourly production by one truck’s hourly production (trips per hour × capacity) and round up. Too few trucks idle the excavator; too many trucks queue.

What is a typical job efficiency?

It depends on the site. Estimators often plan on fewer than 60 working minutes per hour to allow for delays; enter the value your company uses.

Sources

  1. Commercial Vehicle Dimension and Weight Regulation, Alta Reg 315/2002, s. 9 (current as of April 1, 2025)Alberta King's Printer · current as of 2025-04-01