CivilConstruction.ca
Project brief
Concrete pouring from a pump hose into a grid of reinforcing steel inside timber formwork

Unit price group · Sheet D-509

Urban works, curb, concrete and removals: 2026 unit prices

18 tendered items with their 2026 provincial averages, contract counts and two prior years, taken from Alberta's highway contracts.

Sheet D-509Checked 2026-10-253 min read1 source

18Items in this group with a 2026 provincial average
1Items resting on ten or more contracts
27Contracts behind the most-tendered item, Cutting of Pavement1

STA 0+120What this group covers

Urban and intersection work is its own world inside a highway tender: curb and gutter, sidewalk, concrete medians and islands, mechanically stabilized earth (MSE) walls, and the cutting and removal of what is already there. Quantities are typically smaller and the work slower than open-road paving, which tends to push unit prices up.

The 2026 workbook has 18 items in this group; 1 rest on ten or more contracts. Detailed pages: cutting of pavement, curb and gutter.

STA 0+240How these items are priced

Curb and gutter is paid per metre, flatwork and medians per square metre, and removals per metre, square metre or cubic metre of what is taken out. Several items here have only one to three contracts behind them, so the contract count is worth reading before leaning on a number.

STA 0+360Every item, with 2025 and 2024 averages

Each row is the average of the three lowest bids on contracts tendered May 1, 2025 to June 24, 2026. Rows marked low sample rest on fewer than three contracts.

Alberta provincial highway tenders: average unit prices1
ItemUnit2026 avgContracts2025 avg2024 avgvs 2025
Pre-Construction Advertising SignItem X103sign$1,6622low sample———
Asphalt Surfacing - Remove and DisposeItem X205m³$67.634$67.145 contracts$63.834 contracts+1%
Concrete Curb and Gutter - Remove and DisposeItem X215m$32.601low sample———
Concrete Surface - Remove and DisposeItem X220m²$37.265$42.255 contracts$39.538 contracts−12%
Concrete Curb - Remove and DisposeItem X235m$42.052low sample———
Monolithic Sidewalk, Curb and GutterItem X310m$416.143$450.442 contracts$346.213 contracts−8%
Concrete CurbItem X320m$175.243$188.014 contracts—−7%
Curb and GutterItem X325m$183.005$238.708 contracts$156.1510 contracts−23%
Hand-Laid Riprap - Other Locations - Supply and PlaceItem X346m²$153.685———
Solid Concrete IslandsItem X350m²$276.671low sample———
Concrete BarrierItem X355m$548.521low sample$561.151 contract$1,5091 contract−2%
Concrete SwaleItem X360m$248.031low sample———
Mechanically Stabilized Earth (MSE) WallItem X370m²$2,9233———
Solid Concrete MediansItem X400m²$261.671low sample———
Granular Fill for MediansItem X415t$38.321low sample———
Median Concrete SurfacingItem X440m²$179.703———
Cold In-Place RecyclingItem X444m²$17.211low sample———
Cutting of PavementItem X510m$8.4327$11.8931 contracts$10.4029 contracts−29%

STA 0+480The most-tendered items

The contract count is the best guide to how much weight an average can bear. In this group the most-tendered items are:

  • Cutting of Pavement (item X510): $8.43 per m1 from 27 contracts
  • Concrete Surface - Remove and Dispose (item X220): $37.26 per m²1 from 5 contracts
  • Curb and Gutter (item X325): $183.00 per m1 from 5 contracts
  • Hand-Laid Riprap - Other Locations - Supply and Place (item X346): $153.68 per m²1 from 5 contracts
  • Asphalt Surfacing - Remove and Dispose (item X205): $67.63 per m³1 from 4 contracts

STA 0+600Biggest year-on-year changes

Few items in this group have five or more contracts in both 2025 and 2026, so there is no reliable year-on-year comparison to show. The table above gives each item's own history.

STA 0+720Where to go next

Questions people ask

What is in the urban works, curb, concrete and removals group of Alberta's unit price averages?

The 2026 workbook lists 18 items in this group, from Pre-Construction Advertising Sign (item X103) to Cutting of Pavement (item X510). Each is the average of the three lowest bids on Alberta provincial highway contracts.

Which urban works & concrete item is tendered most often?

Cutting of Pavement (item X510) rests on the most contracts in this group, with 27 contracts. Its 2026 average is $8.43 per m1.

Can I use these prices for a private project?

Only as a benchmark. These are highway-scale averages, and small private jobs usually pay more per unit because mobilization, minimum charges and disposal are spread over less work. Send your scope and quantities on the project brief for a real number.

Sources

  1. Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026