Unit price · Sheet D-602
Borrow excavation: 2026 Alberta unit price
What Alberta paid for borrow excavation on provincial highway contracts in 2026, from 15 contracts, and how the average has moved since 2024.
STA 0+120What borrow excavation covers
Borrow is soil or granular material brought in from a separate source, a borrow pit, because the cuts on the job do not supply enough fill. Alberta tenders it under two items in this workbook: borrow excavation (G235) and borrow excavation with the contractor supplying the source (G236).
The workbook gives no description beyond the item names, so what each item includes should be read from the contract documents, not inferred from this page.
STA 0+2402026 prices and three-year history
In 2026 the provincial average for Borrow Excavation - Contractor Supplied (item G236) was $23.67 per m³1, the average of the three lowest bids on 15 contracts tendered May 1, 2025 to June 24, 2026. That is down 1% on the 2025 average of $23.86 (7 contracts) and down 23% on 2024's $30.81 (8 contracts).
| Item | Unit | 2026 avg | Contracts | 2025 avg | 2024 avg | vs 2025 |
|---|---|---|---|---|---|---|
| Borrow Excavation - Contractor SuppliedItem G236 | m³ | $23.67 | 15 | $23.867 contracts | $30.818 contracts | −1% |
| Borrow ExcavationItem G235 | m³ | $15.99 | 6 | $13.051 contract | $12.994 contracts | +23% |
STA 0+360How the price varies across Alberta
Alberta publishes regional averages for some items. For item G236, Southern averaged $39.33 and North Central $22.50, which is 75% higher. Regional gaps like this come from haul distance, local competition and the mix of work tendered in each region.
| Region | Avg per m³ | Contracts |
|---|---|---|
| Southern region | $39.33 | 1 |
| Central region | $23.39 | 9 |
| North Central region | $22.50 | 1 |
| Peace region | $31.76 | 4 |
| Province | $23.67 | 15 |
| Region | Avg per m³ | Contracts |
|---|---|---|
| Central region | $11.82 | 3 |
| North Central region | $20.97 | 3 |
| Province | $15.99 | 6 |
STA 0+480What moves the price
A contractor-supplied source puts finding and securing the pit, access and any lease or royalty on the contractor, on top of digging and loading. That is consistent with G236 averaging more than G235, but the two items come from different contracts, so the gap is indicative and not exact.
Haul from pit to the work, the volume required, and pit quality (clean fill versus material that needs screening) set the rest.
STA 0+600Using the number in a budget
These are benchmarks, not quotes. Each figure is the average of the three lowest bids on Alberta provincial highway contracts, at highway quantities. A small private job pays more per unit because mobilization, minimum charges and disposal are spread over less work.
Use the number to sanity-check a unit rate in a bid or to see which way a price has moved, then ask for a quote that matches your quantities, access and timing.
STA 0+720Related prices, guides and tools
Questions people ask
How much does borrow excavation cost in Alberta?
On Alberta provincial highway tenders in 2026, Borrow Excavation - Contractor Supplied (item G236) averaged $23.67 per m³1, the average of the three lowest bids across 15 contracts. It is a highway-scale benchmark, not a quote for a particular job.
Has the price of borrow excavation gone up?
The 2026 average of $23.67 per m³ is down 1% on the 2025 average of $23.86 and down 23% on 2024's $30.81. Annual averages move with the mix of contracts tendered, so a change in the average is not the same as a change in the cost of the work.
Can I use this price for a small job, or outside Alberta?
Use it as a reference point, not a price. The average reflects highway contracts, so a smaller job usually costs more per unit, and no other province publishes a comparable average for this item. For your own job, send the scope, quantities and location on the project brief and we reply by email.
Why does Alberta list borrow excavation under several item codes?
Each code is a separate tender item with its own specification, and the workbook gives no description beyond the item name. Cite prices by code, and read the contract documents to see what each code includes.
Sources
- Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026