Unit price group · Sheet D-502

Earthwork, clearing, grading and fencing: 2026 unit prices

37 tendered items with their 2026 provincial averages, contract counts and two prior years, taken from Alberta's highway contracts.

Sheet D-502Checked 2026-10-255 min read1 source

37Items in this group with a 2026 provincial average
7Items resting on ten or more contracts
27Contracts behind the most-tendered item, Topsoil Placement1

STA 0+120What this group covers

Earthwork is where most of a road's money and schedule go before any pavement exists: clearing the right of way, stripping and replacing topsoil, cutting and filling, hauling borrow, shaping ditches and fencing the corridor. These items are priced per cubic metre, per hectare, per square metre or per kilometre.

Nearly all of them respond to the same three things: how far material has to move, what the ground is like, and how well the cuts and fills balance. A project that can build its fills from its own cuts is cheap. One that has to import borrow or haul surplus away is not.

The 2026 workbook has 37 items in this group; 7 rest on ten or more contracts. Detailed pages: common excavation, borrow excavation, channel excavation, topsoil placement, clearing and mulching, right-of-way fencing.

STA 0+240How these items are priced

Excavation is paid by the cubic metre moved, clearing by the hectare, topsoil by the square metre placed, and fence by the kilometre. Because the contract sets the quantities, the unit price absorbs mobilization and the site's particular haul and ground conditions, which is why averages for the same item can swing from year to year as the mix of contracts changes.

STA 0+360Every item, with 2025 and 2024 averages

Each row is the average of the three lowest bids on contracts tendered May 1, 2025 to June 24, 2026. Rows marked low sample rest on fewer than three contracts.

Alberta provincial highway tenders: average unit prices1
ItemUnit2026 avgContracts2025 avg2024 avgvs 2025
Topsoil and Subsoil StrippingItem C055m³$8.743———
Topsoil and Subsoil PlacementItem C056m³$8.853———
Common ExcavationItem C060m³$18.161low sample———
Wet Excavation - Type 2Item C064m³$8.642low sample———
Pitrun Gravel Zone 4CItem C090m³$112.461low sample———
Coarse Rip-rap Bedding Zone 5BItem C102m³$96.731low sample———
Gravel Armour Zone 5CItem C105m³$129.522low sample———
Riprap Zone 6BItem C120m³$167.641low sample———
Salvage and Reinstall Existing RiprapItem C143m³$183.511low sample———
Erosion Control BlanketItem C225m²$3.981low sample———
Drill SeedingItem C230m²$4.011low sample———
ClearingItem G100ha$18,2782low sample———
Clearing and MulchingItem G101ha$16,43920$7,35611 contracts$28,0298 contracts+123%
Clearing and Timber SalvageItem G105ha$11,5011low sample———
Clearing, Timber Salvage and MulchingItem G106ha$25,6243———
Solid Rock Excavation - PremiumItem G205m³$44.961low sample———
Rippable Rock Excavation - PremiumItem G210m³$16.532low sample———
Channel ExcavationItem G220m³$19.4219$6.656 contracts$13.6111 contracts+192%
Common ExcavationItem G225m³$11.2024$8.9613 contracts$10.8926 contracts+25%
Borrow Topsoil ExcavationItem G230m³$4.876$9.421 contract$4.753 contracts−48%
Borrow ExcavationItem G235m³$15.996$13.051 contract$12.994 contracts+23%
Borrow Excavation - Contractor SuppliedItem G236m³$23.6715$23.867 contracts$30.818 contracts−1%
OverhaulItem G239cubic metre kilometre$1.605———
Common and/or Borrow Excavation Loaded to TrucksItem G248m³$15.199———
Truck Haul of Common and/or Borrow ExcavationItem G249cubic metre kilometre$0.493———
Catch Water DitchesItem G260m$43.672low sample———
Sideslope ImprovementItem G270km$66,3564———
Topsoil PlacementItem G300m²$1.1327$1.1116 contracts$1.3524 contracts+2%
Borrow ReclamationItem G301m²$1.106———
Remove and Dispose of Existing FenceItem G452km$4,58214———
Taking Down and Re-erecting Existing FenceItem G455km$36,1501low sample———
New Fence - Supply and Install - Class AItem G470km$13,2122low sample———
New Fence - Supply and Install - Class BItem G475km$16,80124$39,4469 contracts$16,29713 contracts−57%
New Fence - Supply and Install - Class CItem G480km$23,2392low sample———
New Fence - Supply and Install - Class EItem G482km$38,6112low sample———
New Fence - Supply and Install - Class FItem G483km$190,6963———
New Fence - Supply and Install - Class HItem G496m$2,5031low sample———

STA 0+480The most-tendered items

The contract count is the best guide to how much weight an average can bear. In this group the most-tendered items are:

STA 0+600Biggest year-on-year changes

Among the 6 items in this group with five or more contracts in both 2025 and 2026, these moved most. Annual averages shift with the mix of contracts tendered, so a big move can reflect a few unusual jobs.

Item2025 avg2026 avgChange
Channel ExcavationItem G220 · per m³$6.65$19.42+192%
Clearing and MulchingItem G101 · per ha$7,356$16,439+123%
Common ExcavationItem G225 · per m³$8.96$11.20+25%
New Fence - Supply and Install - Class BItem G475 · per km$39,446$16,801−57%
Borrow Excavation - Contractor SuppliedItem G236 · per m³$23.86$23.67−1%
Topsoil PlacementItem G300 · per m²$1.11$1.13+2%

STA 0+720Where to go next

Questions people ask

What is in the earthwork, clearing, grading and fencing group of Alberta's unit price averages?

The 2026 workbook lists 37 items in this group, from Topsoil and Subsoil Stripping (item C055) to New Fence - Supply and Install - Class H (item G496). Each is the average of the three lowest bids on Alberta provincial highway contracts.

Which earthwork & grading item is tendered most often?

Topsoil Placement (item G300) rests on the most contracts in this group, with 27 contracts. Its 2026 average is $1.13 per m²1.

Can I use these prices for a private project?

Only as a benchmark. These are highway-scale averages, and small private jobs usually pay more per unit because mobilization, minimum charges and disposal are spread over less work. Send your scope and quantities on the project brief for a real number.

Sources

  1. Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026