Unit price group · Sheet D-502
Earthwork, clearing, grading and fencing: 2026 unit prices
37 tendered items with their 2026 provincial averages, contract counts and two prior years, taken from Alberta's highway contracts.
STA 0+120What this group covers
Earthwork is where most of a road's money and schedule go before any pavement exists: clearing the right of way, stripping and replacing topsoil, cutting and filling, hauling borrow, shaping ditches and fencing the corridor. These items are priced per cubic metre, per hectare, per square metre or per kilometre.
Nearly all of them respond to the same three things: how far material has to move, what the ground is like, and how well the cuts and fills balance. A project that can build its fills from its own cuts is cheap. One that has to import borrow or haul surplus away is not.
The 2026 workbook has 37 items in this group; 7 rest on ten or more contracts. Detailed pages: common excavation, borrow excavation, channel excavation, topsoil placement, clearing and mulching, right-of-way fencing.
STA 0+240How these items are priced
Excavation is paid by the cubic metre moved, clearing by the hectare, topsoil by the square metre placed, and fence by the kilometre. Because the contract sets the quantities, the unit price absorbs mobilization and the site's particular haul and ground conditions, which is why averages for the same item can swing from year to year as the mix of contracts changes.
STA 0+360Every item, with 2025 and 2024 averages
Each row is the average of the three lowest bids on contracts tendered May 1, 2025 to June 24, 2026. Rows marked low sample rest on fewer than three contracts.
| Item | Unit | 2026 avg | Contracts | 2025 avg | 2024 avg | vs 2025 |
|---|---|---|---|---|---|---|
| Topsoil and Subsoil StrippingItem C055 | m³ | $8.74 | 3 | — | — | — |
| Topsoil and Subsoil PlacementItem C056 | m³ | $8.85 | 3 | — | — | — |
| Common ExcavationItem C060 | m³ | $18.16 | 1low sample | — | — | — |
| Wet Excavation - Type 2Item C064 | m³ | $8.64 | 2low sample | — | — | — |
| Pitrun Gravel Zone 4CItem C090 | m³ | $112.46 | 1low sample | — | — | — |
| Coarse Rip-rap Bedding Zone 5BItem C102 | m³ | $96.73 | 1low sample | — | — | — |
| Gravel Armour Zone 5CItem C105 | m³ | $129.52 | 2low sample | — | — | — |
| Riprap Zone 6BItem C120 | m³ | $167.64 | 1low sample | — | — | — |
| Salvage and Reinstall Existing RiprapItem C143 | m³ | $183.51 | 1low sample | — | — | — |
| Erosion Control BlanketItem C225 | m² | $3.98 | 1low sample | — | — | — |
| Drill SeedingItem C230 | m² | $4.01 | 1low sample | — | — | — |
| ClearingItem G100 | ha | $18,278 | 2low sample | — | — | — |
| Clearing and MulchingItem G101 | ha | $16,439 | 20 | $7,35611 contracts | $28,0298 contracts | +123% |
| Clearing and Timber SalvageItem G105 | ha | $11,501 | 1low sample | — | — | — |
| Clearing, Timber Salvage and MulchingItem G106 | ha | $25,624 | 3 | — | — | — |
| Solid Rock Excavation - PremiumItem G205 | m³ | $44.96 | 1low sample | — | — | — |
| Rippable Rock Excavation - PremiumItem G210 | m³ | $16.53 | 2low sample | — | — | — |
| Channel ExcavationItem G220 | m³ | $19.42 | 19 | $6.656 contracts | $13.6111 contracts | +192% |
| Common ExcavationItem G225 | m³ | $11.20 | 24 | $8.9613 contracts | $10.8926 contracts | +25% |
| Borrow Topsoil ExcavationItem G230 | m³ | $4.87 | 6 | $9.421 contract | $4.753 contracts | −48% |
| Borrow ExcavationItem G235 | m³ | $15.99 | 6 | $13.051 contract | $12.994 contracts | +23% |
| Borrow Excavation - Contractor SuppliedItem G236 | m³ | $23.67 | 15 | $23.867 contracts | $30.818 contracts | −1% |
| OverhaulItem G239 | cubic metre kilometre | $1.60 | 5 | — | — | — |
| Common and/or Borrow Excavation Loaded to TrucksItem G248 | m³ | $15.19 | 9 | — | — | — |
| Truck Haul of Common and/or Borrow ExcavationItem G249 | cubic metre kilometre | $0.49 | 3 | — | — | — |
| Catch Water DitchesItem G260 | m | $43.67 | 2low sample | — | — | — |
| Sideslope ImprovementItem G270 | km | $66,356 | 4 | — | — | — |
| Topsoil PlacementItem G300 | m² | $1.13 | 27 | $1.1116 contracts | $1.3524 contracts | +2% |
| Borrow ReclamationItem G301 | m² | $1.10 | 6 | — | — | — |
| Remove and Dispose of Existing FenceItem G452 | km | $4,582 | 14 | — | — | — |
| Taking Down and Re-erecting Existing FenceItem G455 | km | $36,150 | 1low sample | — | — | — |
| New Fence - Supply and Install - Class AItem G470 | km | $13,212 | 2low sample | — | — | — |
| New Fence - Supply and Install - Class BItem G475 | km | $16,801 | 24 | $39,4469 contracts | $16,29713 contracts | −57% |
| New Fence - Supply and Install - Class CItem G480 | km | $23,239 | 2low sample | — | — | — |
| New Fence - Supply and Install - Class EItem G482 | km | $38,611 | 2low sample | — | — | — |
| New Fence - Supply and Install - Class FItem G483 | km | $190,696 | 3 | — | — | — |
| New Fence - Supply and Install - Class HItem G496 | m | $2,503 | 1low sample | — | — | — |
STA 0+480The most-tendered items
The contract count is the best guide to how much weight an average can bear. In this group the most-tendered items are:
- Topsoil Placement (item G300): $1.13 per m²1 from 27 contracts
- Common Excavation (item G225): $11.20 per m³1 from 24 contracts
- New Fence - Supply and Install - Class B (item G475): $16,801 per km1 from 24 contracts
- Clearing and Mulching (item G101): $16,439 per ha1 from 20 contracts
- Channel Excavation (item G220): $19.42 per m³1 from 19 contracts
STA 0+600Biggest year-on-year changes
Among the 6 items in this group with five or more contracts in both 2025 and 2026, these moved most. Annual averages shift with the mix of contracts tendered, so a big move can reflect a few unusual jobs.
| Item | 2025 avg | 2026 avg | Change |
|---|---|---|---|
| Channel ExcavationItem G220 · per m³ | $6.65 | $19.42 | +192% |
| Clearing and MulchingItem G101 · per ha | $7,356 | $16,439 | +123% |
| Common ExcavationItem G225 · per m³ | $8.96 | $11.20 | +25% |
| New Fence - Supply and Install - Class BItem G475 · per km | $39,446 | $16,801 | −57% |
| Borrow Excavation - Contractor SuppliedItem G236 · per m³ | $23.86 | $23.67 | −1% |
| Topsoil PlacementItem G300 · per m² | $1.11 | $1.13 | +2% |
STA 0+720Where to go next
Questions people ask
What is in the earthwork, clearing, grading and fencing group of Alberta's unit price averages?
The 2026 workbook lists 37 items in this group, from Topsoil and Subsoil Stripping (item C055) to New Fence - Supply and Install - Class H (item G496). Each is the average of the three lowest bids on Alberta provincial highway contracts.
Which earthwork & grading item is tendered most often?
Topsoil Placement (item G300) rests on the most contracts in this group, with 27 contracts. Its 2026 average is $1.13 per m²1.
Can I use these prices for a private project?
Only as a benchmark. These are highway-scale averages, and small private jobs usually pay more per unit because mobilization, minimum charges and disposal are spread over less work. Send your scope and quantities on the project brief for a real number.
Sources
- Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026