Unit price · Sheet D-601

Common excavation: 2026 Alberta unit price

What Alberta paid for common excavation on provincial highway contracts in 2026, from 24 contracts, and how the average has moved since 2024.

Sheet D-601Checked 2026-10-252 min read1 source

$11.20/m³Alberta 2026 average, item G2251
+25%Change from the 2025 average of $8.96
24Contracts behind the 2026 average

STA 0+120What common excavation covers

Common excavation is the bulk earthmoving line on a highway or road job: digging ordinary soil, meaning clay, silt, sand and gravel that a machine can excavate without blasting or ripping, and moving it to where the design needs it. It pays for the cuts in a road grade, for ditches, and for building embankments out of on-site material.

Rock, topsoil and borrow material are paid under their own items, so this is the base earthwork rate and not an all-in figure for moving a site.

STA 0+2402026 price and three-year history

In 2026 the provincial average for Common Excavation (item G225) was $11.20 per m³1, the average of the three lowest bids on 24 contracts tendered May 1, 2025 to June 24, 2026. That is up 25% on the 2025 average of $8.96 (13 contracts) and up 3% on 2024's $10.89 (26 contracts).

Common excavation: three-year history1
ItemUnit2026 avgContracts2025 avg2024 avgvs 2025
Common ExcavationItem G225m³$11.2024$8.9613 contracts$10.8926 contracts+25%

STA 0+360How the price varies across Alberta

Alberta publishes regional averages for some items. For item G225, North Central averaged $14.21 and Central $8.37, which is 70% higher. Regional gaps like this come from haul distance, local competition and the mix of work tendered in each region.

Common Excavation (item G225), 2026 average by Alberta region1
RegionAvg per m³Contracts
Southern region$10.822
Central region$8.3712
North Central region$14.214
Peace region$10.466
Province$11.2024

STA 0+480What moves the price

Haul distance is the biggest swing factor. A short cut-to-fill move costs a fraction of trucking material across a project or off site. Soil type and moisture come next: wet clay slows machines and may need drying or a deeper dig.

Job size spreads mobilization over more cubic metres, the season changes productivity (frost, mud, daylight), and fuel and equipment availability set the hourly cost underneath it all.

STA 0+600Using the number in a budget

These are benchmarks, not quotes. Each figure is the average of the three lowest bids on Alberta provincial highway contracts, at highway quantities: contracts in this sample averaged about 160,000 m³ of this item. A small private job pays more per unit because mobilization, minimum charges and disposal are spread over less work.

Arithmetic only: 20,000 m³ at the provincial average is $224,000, before any small-job premium. Use the number to sanity-check a unit rate in a bid or to see which way a price has moved, then ask for a quote that matches your quantities, access and timing.

STA 0+720Related prices, guides and tools

Questions people ask

How much does common excavation cost in Alberta?

On Alberta provincial highway tenders in 2026, Common Excavation (item G225) averaged $11.20 per m³1, the average of the three lowest bids across 24 contracts. It is a highway-scale benchmark, not a quote for a particular job.

Has the price of common excavation gone up?

The 2026 average of $11.20 per m³ is up 25% on the 2025 average of $8.96 and up 3% on 2024's $10.89. Annual averages move with the mix of contracts tendered, so a change in the average is not the same as a change in the cost of the work.

Can I use this price for a small job, or outside Alberta?

Use it as a reference point, not a price. The average reflects highway contracts that averaged about 160,000 m³ of this item, so a smaller job usually costs more per unit, and no other province publishes a comparable average for this item. For your own job, send the scope, quantities and location on the project brief and we reply by email.

Sources

  1. Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026