Unit price · Sheet D-606
Subgrade preparation: 2026 Alberta unit price
What Alberta paid for subgrade preparation on provincial highway contracts in 2026, from 21 contracts, and how the average has moved since 2024.
STA 0+120What subgrade preparation covers
Preparing the subgrade surface means trimming, shaping and compacting the top of the earthwork to grade so the granular base can be placed on it. It is priced per square metre prepared, and sits between earthwork and the first gravel on every new or rebuilt road. Alberta lists a first-layer item (B180) and a second-layer item (B181).
STA 0+2402026 prices and three-year history
In 2026 the provincial average for Preparing Subgrade Surface (First Layer) (item B180) was $2.03 per m²1, the average of the three lowest bids on 21 contracts tendered May 1, 2025 to June 24, 2026. That is up 30% on the 2025 average of $1.56 (11 contracts) and down 13% on 2024's $2.32 (17 contracts).
| Item | Unit | 2026 avg | Contracts | 2025 avg | 2024 avg | vs 2025 |
|---|---|---|---|---|---|---|
| Preparing Subgrade Surface (First Layer)Item B180 | m² | $2.03 | 21 | $1.5611 contracts | $2.3217 contracts | +30% |
| Preparing Subgrade Surface (Second Layer)Item B181 | m² | $0.80 | 1low sample | — | — | — |
Items marked low sample rest on fewer than three contracts. Treat them as a single data point.
STA 0+360How the price varies across Alberta
Alberta reports regional averages for only a minority of items, and none for subgrade preparation. The provincial average above is the only published figure, so a region with long hauls or little competition will usually price above it.
STA 0+480What moves the price
Soil type and moisture decide how much compaction effort, drying or stabilization the surface needs; a wet or soft subgrade can multiply the work. Contract size, the width of the work area, the grade tolerance required and the weather window set the rest.
STA 0+600Using the number in a budget
These are benchmarks, not quotes. Each figure is the average of the three lowest bids on Alberta provincial highway contracts, at highway quantities: contracts in this sample averaged about 78,000 m² of this item. A small private job pays more per unit because mobilization, minimum charges and disposal are spread over less work.
Arithmetic only: 8,000 m² at the provincial average is $16,240, before any small-job premium. Use the number to sanity-check a unit rate in a bid or to see which way a price has moved, then ask for a quote that matches your quantities, access and timing.
STA 0+720Related prices, guides and tools
Questions people ask
How much does subgrade preparation cost in Alberta?
On Alberta provincial highway tenders in 2026, Preparing Subgrade Surface (First Layer) (item B180) averaged $2.03 per m²1, the average of the three lowest bids across 21 contracts. It is a highway-scale benchmark, not a quote for a particular job.
Has the price of subgrade preparation gone up?
The 2026 average of $2.03 per m² is up 30% on the 2025 average of $1.56 and down 13% on 2024's $2.32. Annual averages move with the mix of contracts tendered, so a change in the average is not the same as a change in the cost of the work.
Can I use this price for a small job, or outside Alberta?
Use it as a reference point, not a price. The average reflects highway contracts that averaged about 78,000 m² of this item, so a smaller job usually costs more per unit, and no other province publishes a comparable average for this item. For your own job, send the scope, quantities and location on the project brief and we reply by email.
Why does Alberta list subgrade preparation under several item codes?
Each code is a separate tender item with its own specification, and the workbook gives no description beyond the item name. Cite prices by code, and read the contract documents to see what each code includes.
Sources
- Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026