Unit price · Sheet D-613

Seeding and hydro-seeding: 2026 Alberta unit price

What Alberta paid for seeding and hydro-seeding on provincial highway contracts in 2026, from 23 contracts, and how the average has moved since 2024.

Sheet D-613Checked 2026-10-252 min read1 source

$2,716/haAlberta 2026 average, item E6081
−11%Change from the 2025 average of $3,044
23Contracts behind the 2026 average

STA 0+120What seeding and hydro-seeding covers

Seeding establishes vegetation on disturbed ground. Alberta prices three methods per hectare: broad-cast seeding (E608), drill seeding (E607) and hydro-seeding (E609), where seed, mulch and tackifier are sprayed as a slurry. Hydro-seeding costs several times more per hectare than broad-cast, which is why it tends to be used on slopes and sensitive sites where the cheaper methods do not work.

STA 0+2402026 prices and three-year history

In 2026 the provincial average for Broad-Cast Seeding (item E608) was $2,716 per ha1, the average of the three lowest bids on 23 contracts tendered May 1, 2025 to June 24, 2026. That is down 11% on the 2025 average of $3,044 (9 contracts) and up 30% on 2024's $2,097 (14 contracts).

Seeding and hydro-seeding: every item code in the workbook1
ItemUnit2026 avgContracts2025 avg2024 avgvs 2025
Broad-Cast SeedingItem E608ha$2,71623$3,0449 contracts$2,09714 contracts−11%
Hydro-SeedingItem E609ha$12,58215$10,6783 contracts$12,5648 contracts+18%
Drill SeedingItem E607ha$4,0154———

STA 0+360How the price varies across Alberta

Alberta publishes regional averages for some items. For item E608, North Central averaged $4,297 and Central $2,194, which is 96% higher. Regional gaps like this come from haul distance, local competition and the mix of work tendered in each region.

Broad-Cast Seeding (item E608), 2026 average by Alberta region1
RegionAvg per haContracts
Central region$2,19410
North Central region$4,2977
Peace region$3,2246
Province$2,71623
Hydro-Seeding (item E609), 2026 average by Alberta region1
RegionAvg per haContracts
Southern region$8,6311
Central region$27,7039
North Central region$10,9732
Peace region$22,3873
Province$12,58215

STA 0+480What moves the price

Slope and access decide the method, and the method decides the price. Seed mix, the season (seed needs time to germinate before freeze-up), the area per contract and any requirement for mulch or tackifier follow.

STA 0+600Using the number in a budget

These are benchmarks, not quotes. Each figure is the average of the three lowest bids on Alberta provincial highway contracts, at highway quantities. A small private job pays more per unit because mobilization, minimum charges and disposal are spread over less work.

Use the number to sanity-check a unit rate in a bid or to see which way a price has moved, then ask for a quote that matches your quantities, access and timing.

STA 0+720Related prices, guides and tools

Questions people ask

How much does seeding and hydro-seeding cost in Alberta?

On Alberta provincial highway tenders in 2026, Broad-Cast Seeding (item E608) averaged $2,716 per ha1, the average of the three lowest bids across 23 contracts. It is a highway-scale benchmark, not a quote for a particular job.

Has the price of seeding and hydro-seeding gone up?

The 2026 average of $2,716 per ha is down 11% on the 2025 average of $3,044 and up 30% on 2024's $2,097. Annual averages move with the mix of contracts tendered, so a change in the average is not the same as a change in the cost of the work.

Can I use this price for a small job, or outside Alberta?

Use it as a reference point, not a price. The average reflects highway contracts, so a smaller job usually costs more per unit, and no other province publishes a comparable average for this item. For your own job, send the scope, quantities and location on the project brief and we reply by email.

Why does Alberta list seeding and hydro-seeding under several item codes?

Each code is a separate tender item with its own specification, and the workbook gives no description beyond the item name. Cite prices by code, and read the contract documents to see what each code includes.

Sources

  1. Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026