Erosion control, geosynthetics and seeding: 2026 unit prices

16 tendered items with their 2026 provincial averages, contract counts and two prior years, taken from Alberta's highway contracts.

Sheet D-504Checked 2026-10-253 min read1 source

16Items in this group with a 2026 provincial average
6Items resting on ten or more contracts
32Contracts behind the most-tendered item, Erosion Control Soil Covering - Supply and Install (Type B)1

STA 0+120What this group covers

When a road or site is built, bare ground is exposed for months, and rain moves that soil into ditches and watercourses unless something stops it. This group is the something: silt fence and straw barriers while work is underway, blankets and soil coverings on finished slopes, geotextile and geogrid under and inside fills, gabions where a slope needs structure, and seeding to establish vegetation.

These are low-dollar, high-count items that appear on many contracts, so several of their averages rest on more contracts than most other groups.

The 2026 workbook has 16 items in this group; 6 rest on ten or more contracts. Detailed pages: silt fence, erosion control soil covering, seeding and hydro-seeding.

STA 0+240How these items are priced

Barriers are paid per metre, blankets and geotextile per square metre, and seeding per hectare. Prices depend on the product and on how much of the work is on steep slopes or in awkward access, and seeding is also tied to the season, since seed has to go down when it can germinate.

STA 0+360Every item, with 2025 and 2024 averages

Each row is the average of the three lowest bids on contracts tendered May 1, 2025 to June 24, 2026. Rows marked low sample rest on fewer than three contracts.

Alberta provincial highway tenders: average unit prices1
ItemUnit2026 avgContracts2025 avg2024 avgvs 2025
Gabion Baskets - Supply and InstallItem E325m³$1,1651low sample———
Gabion Mattress - Supply and InstallItem E331m²$583.112low sample———
Straw Bale BarrierItem E405m$20.637———
Erosion Control Barrier (Silt Fence)Item E435m$14.3021$11.1016 contracts$17.0925 contracts+29%
Non-Woven Geotextile - Supply and InstallItem E452m²$4.983———
Geogrid - Supply and InstallItem E453m²$7.626———
Geotextile for Materials Separation - Supply and InstallItem E454m²$10.871low sample———
Geotextile for Stabilization - Supply and InstallItem E456m²$9.501low sample———
Erosion Control Soil Covering - Supply and Install (Type A)Item E500m²$4.031low sample———
Erosion Control Soil Covering - Supply and Install (Type B)Item E505m²$5.8932$13.577 contracts$4.6013 contracts−57%
Erosion Control Soil Covering - Supply and Install (Type C)Item E510m²$5.1722———
Synthetic Permeable Ditch BarrierItem E515m$31.023———
Drill SeedingItem E607ha$4,0154———
Broad-Cast SeedingItem E608ha$2,71623$3,0449 contracts$2,09714 contracts−11%
Hydro-SeedingItem E609ha$12,58215$10,6783 contracts$12,5648 contracts+18%
Slope TexturingItem E610m²$0.8113———

STA 0+480The most-tendered items

The contract count is the best guide to how much weight an average can bear. In this group the most-tendered items are:

STA 0+600Biggest year-on-year changes

Few items in this group have five or more contracts in both 2025 and 2026, so there is no reliable year-on-year comparison to show. The table above gives each item's own history.

STA 0+720Where to go next

Questions people ask

What is in the erosion control, geosynthetics and seeding group of Alberta's unit price averages?

The 2026 workbook lists 16 items in this group, from Gabion Baskets - Supply and Install (item E325) to Slope Texturing (item E610). Each is the average of the three lowest bids on Alberta provincial highway contracts.

Which erosion control & seeding item is tendered most often?

Erosion Control Soil Covering - Supply and Install (Type B) (item E505) rests on the most contracts in this group, with 32 contracts. Its 2026 average is $5.89 per m²1.

Can I use these prices for a private project?

Only as a benchmark. These are highway-scale averages, and small private jobs usually pay more per unit because mobilization, minimum charges and disposal are spread over less work. Send your scope and quantities on the project brief for a real number.

Sources

  1. Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026