Unit price · Sheet D-612
Erosion control soil covering: 2026 Alberta unit price
What Alberta paid for erosion control soil covering on provincial highway contracts in 2026, from 32 contracts, and how the average has moved since 2024.
STA 0+120What erosion control soil covering covers
Erosion control soil covering is the blanket or mat laid over a finished slope or ditch to hold soil and seed in place until plants take over. The workbook prices three product types (A, B and C) as separate items per square metre.
Type B is among the most-tendered items in the workbook, so its average rests on far more contracts than most.
STA 0+2402026 prices and three-year history
In 2026 the provincial average for Erosion Control Soil Covering - Supply and Install (Type B) (item E505) was $5.89 per m²1, the average of the three lowest bids on 32 contracts tendered May 1, 2025 to June 24, 2026. That is down 57% on the 2025 average of $13.57 (7 contracts) and up 28% on 2024's $4.60 (13 contracts).
| Item | Unit | 2026 avg | Contracts | 2025 avg | 2024 avg | vs 2025 |
|---|---|---|---|---|---|---|
| Erosion Control Soil Covering - Supply and Install (Type B)Item E505 | m² | $5.89 | 32 | $13.577 contracts | $4.6013 contracts | −57% |
| Erosion Control Soil Covering - Supply and Install (Type A)Item E500 | m² | $4.03 | 1low sample | — | — | — |
| Erosion Control Soil Covering - Supply and Install (Type C)Item E510 | m² | $5.17 | 22 | — | — | — |
Read the swings with care. Item E505 moved by a factor of 3.0 between its highest and lowest annual average. Averages like these usually reflect which contracts happened to be tendered in a given year more than a change in the cost of the work.
Items marked low sample rest on fewer than three contracts. Treat them as a single data point.
STA 0+360How the price varies across Alberta
Alberta reports regional averages for only a minority of items, and none for erosion control soil covering. The provincial average above is the only published figure, so a region with long hauls or little competition will usually price above it.
STA 0+480What moves the price
Product type and weight, slope steepness, how much the contractor has to cut and pin, and access for crews carrying rolls up a slope all drive the price. A large contract count steadies an average but does not remove the effect of a few big jobs with very different slopes.
STA 0+600Using the number in a budget
These are benchmarks, not quotes. Each figure is the average of the three lowest bids on Alberta provincial highway contracts, at highway quantities: contracts in this sample averaged about 4,500 m² of this item. A small private job pays more per unit because mobilization, minimum charges and disposal are spread over less work.
Arithmetic only: 400 m² at the provincial average is $2,356, before any small-job premium. Use the number to sanity-check a unit rate in a bid or to see which way a price has moved, then ask for a quote that matches your quantities, access and timing.
STA 0+720Related prices, guides and tools
Questions people ask
How much does erosion control soil covering cost in Alberta?
On Alberta provincial highway tenders in 2026, Erosion Control Soil Covering - Supply and Install (Type B) (item E505) averaged $5.89 per m²1, the average of the three lowest bids across 32 contracts. It is a highway-scale benchmark, not a quote for a particular job.
Has the price of erosion control soil covering gone up?
The 2026 average of $5.89 per m² is down 57% on the 2025 average of $13.57 and up 28% on 2024's $4.60. Annual averages move with the mix of contracts tendered, so a change in the average is not the same as a change in the cost of the work.
Can I use this price for a small job, or outside Alberta?
Use it as a reference point, not a price. The average reflects highway contracts that averaged about 4,500 m² of this item, so a smaller job usually costs more per unit, and no other province publishes a comparable average for this item. For your own job, send the scope, quantities and location on the project brief and we reply by email.
Why does Alberta list erosion control soil covering under several item codes?
Each code is a separate tender item with its own specification, and the workbook gives no description beyond the item name. Cite prices by code, and read the contract documents to see what each code includes.