Street lighting and electrical: 2026 unit prices
9 tendered items with their 2026 provincial averages, contract counts and two prior years, taken from Alberta's highway contracts.
STA 0+120What this group covers
Lighting items cover the poles, bases, cable and enclosures that light an interchange or an urban intersection, along with the trenching to bury the cable. They are priced per unit or per metre, and a single contract can include only a few of them, which makes the contract counts small compared with road items.
The 2026 workbook has 9 items in this group; 3 rest on ten or more contracts. Detailed pages: street light standards.
STA 0+240How these items are priced
Standards, bases and enclosures are paid per unit installed; trenching and cable per metre. Prices are driven by the size of the installation, the depth and type of trench, and whether existing poles are salvaged and reinstalled.
STA 0+360Every item, with 2025 and 2024 averages
Each row is the average of the three lowest bids on contracts tendered May 1, 2025 to June 24, 2026. Rows marked low sample rest on fewer than three contracts.
| Item | Unit | 2026 avg | Contracts | 2025 avg | 2024 avg | vs 2025 |
|---|---|---|---|---|---|---|
| Trenching and BackfillingItem U100 | m | $30.74 | 14 | — | — | — |
| Secondary Cable - Supply and InstallItem U105 | m | $40.22 | 16 | — | — | — |
| Removal and Salvage of Existing StandardsItem U110 | unit | $3,512 | 5 | — | — | — |
| Removal and Disposal of Existing Light FixturesItem U115 | unit | $3,331 | 5 | — | — | — |
| Cast-In-Place Concrete Street Light Base - Supply and InstallItem U120 | unit | $5,408 | 5 | — | — | — |
| Pre-Cast Concrete Street Light Base - Supply and InstallItem U122 | unit | $3,955 | 8 | — | — | — |
| Street Light Standard - Supply and InstallItem U125 | unit | $5,428 | 12 | $5,53311 contracts | $9,3519 contracts | −2% |
| Salvaged Street Light Standard - InstallItem U130 | pole | $2,890 | 5 | — | — | — |
| Distribution Enclosure - Supply and InstallItem U135 | unit | $20,463 | 7 | — | — | — |
STA 0+480The most-tendered items
The contract count is the best guide to how much weight an average can bear. In this group the most-tendered items are:
- Secondary Cable - Supply and Install (item U105): $40.22 per m1 from 16 contracts
- Trenching and Backfilling (item U100): $30.74 per m1 from 14 contracts
- Street Light Standard - Supply and Install (item U125): $5,428 per unit1 from 12 contracts
- Pre-Cast Concrete Street Light Base - Supply and Install (item U122): $3,955 per unit1 from 8 contracts
- Distribution Enclosure - Supply and Install (item U135): $20,463 per unit1 from 7 contracts
STA 0+600Biggest year-on-year changes
Few items in this group have five or more contracts in both 2025 and 2026, so there is no reliable year-on-year comparison to show. The table above gives each item's own history.
STA 0+720Where to go next
Questions people ask
What is in the street lighting and electrical group of Alberta's unit price averages?
The 2026 workbook lists 9 items in this group, from Trenching and Backfilling (item U100) to Distribution Enclosure - Supply and Install (item U135). Each is the average of the three lowest bids on Alberta provincial highway contracts.
Which lighting & electrical item is tendered most often?
Secondary Cable - Supply and Install (item U105) rests on the most contracts in this group, with 16 contracts. Its 2026 average is $40.22 per m1.
Can I use these prices for a private project?
Only as a benchmark. These are highway-scale averages, and small private jobs usually pay more per unit because mobilization, minimum charges and disposal are spread over less work. Send your scope and quantities on the project brief for a real number.
Sources
- Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026
Related
-
D-624
Street light standards
$5,428 per unit · 12 contracts
-
D-501
Aggregate supply and granular base
Aggregate supply, granular fill, subgrade preparation and granular base course, mostly priced per tonne.
-
D-502
Earthwork, clearing, grading and fencing
Common and borrow excavation, topsoil, clearing, riprap bedding, ditches and right-of-way fencing.