Project brief
A concrete highway bridge under construction over a turquoise mountain river with a tower crane

Unit price group · Sheet D-505

Bridges, structural concrete, piling and riprap: 2026 unit prices

44 tendered items with their 2026 provincial averages, contract counts and two prior years, taken from Alberta's highway contracts.

Sheet D-505Checked 2026-10-255 min read1 source

44Items in this group with a 2026 provincial average
16Items resting on ten or more contracts
38Contracts behind the most-tendered item, Heavy Rock Riprap (Class 1)1

STA 0+120What this group covers

This group has some of the highest unit prices in the workbook. Structural concrete runs into the thousands of dollars per cubic metre, piles are priced per metre driven plus a set-up charge per pile, and deck repairs run into the thousands of dollars per square metre.

Structure items depend on the bridge: its size, its access, whether it is over water, and whether work can be done in the dry. That makes the averages useful as orders of magnitude and unreliable as predictions for one structure.

The 2026 workbook has 44 items in this group; 16 rest on ten or more contracts. Detailed pages: heavy rock riprap, structural concrete, reinforcing steel, steel piling, bridge deck waterproofing.

STA 0+240How these items are priced

Concrete is paid per cubic metre, reinforcing steel per kilogram (supply and placing as separate items), piling per metre plus a set-up charge per pile, and riprap per cubic metre. Splitting supply from placement lets you see how much of a price is the material and how much is the labour and equipment to put it in.

STA 0+360Every item, with 2025 and 2024 averages

Each row is the average of the three lowest bids on contracts tendered May 1, 2025 to June 24, 2026. Rows marked low sample rest on fewer than three contracts.

Alberta provincial highway tenders: average unit prices1
ItemUnit2026 avgContracts2025 avg2024 avgvs 2025
Excavation - StructuralItem F188m³$39.742low sample———
Excavation - ChannelItem F189m³$30.001low sample———
Backfill - Non-GranularItem F195m³$24.832low sample———
Backfill - GranularItem F200m³$90.001low sample———
Backfill - Crushed GranularItem F203m³$86.863———
SPCSP - SupplyItem F493m$2,8657———
SPCSP - AssemblyItem F494m$1,7777———
CSP with Couplers - SupplyItem F495m$1,2207———
CSP - AssemblyItem F496m$740.337———
Heavy Rock Riprap (Class 1)Item F500m³$292.5538$315.1521 contracts$342.7522 contracts−7%
Heavy Rock Riprap (Class 1M)Item F505m³$288.5711———
Heavy Rock Riprap (Class 2)Item F515m³$266.809———
Heavy Rock Riprap (Class 3)Item F525m³$426.331low sample———
Concrete Slope ProtectionItem F595m²$481.703———
Concrete End TreatmentItem F655unit$50,1481low sample———
Fish Baffles - SteelItem F715unit$1,1672low sample———
Surface RemovalItem F755m²$97.5412———
Partial Depth RepairItem F760m²$2,23321———
Full Depth RepairItem F765m²$5,1499———
Sandblasting - Bridge DeckItem F770m²$24.609———
Deck Overlay Concrete - SupplyItem F775m³$1,9097———
Deck Overlay Concrete - PlaceItem F776m²$129.757$366.671 contract$172.625 contracts−65%
Supply of Piling - Plain Steel H-PileItem F812m$262.8616$189.9310 contracts$321.459 contracts+38%
Supply of Piling - Galvanized Steel H-PileItem F813m$398.185———
Supply of Piling - Plain Steel Pipe PileItem F814m$452.683———
Supply of Piling - Galvanized Steel Pipe PileItem F815m$697.173———
Pile Set-up (Driven Piles)Item F816pile$4,65218———
Pile DrivingItem F818m$61.1418$45.088 contracts$56.9711 contracts+36%
Dynamic Load Testing/Pile Driving Analyzer (PDA)Item F820test$2,66912———
Concrete - PileItem F822m³$1,2379$749.392 contracts$1,1663 contracts+65%
Drill Rig Set-up (Drilled Piles)Item F824pile$2,6849———
Pile InstallationItem F826m$540.789———
Concrete - Class CItem F834m³$3,31619$2,9298 contracts$2,48512 contracts+13%
Concrete - Class HPCItem F841m³$4,13321$3,13511 contracts$2,8248 contracts+32%
Plain Reinforcing Steel - SupplyItem F850kg$2.9419$2.906 contracts$4.279 contracts+1%
Corrosion Resistant Reinforcing Steel - SupplyItem F851kg$11.0418———
Stainless Reinforcing Steel - SupplyItem F853kg$11.4115———
Reinforcing Steel - PlaceItem F854kg$2.5428$2.4113 contracts$2.9415 contracts+5%
Deck WaterproofingItem F974m²$84.6819$133.4213 contracts$109.7210 contracts−37%
Asphalt Concrete PavementItem F978t$351.331low sample———
Asphalt Concrete PavementItem F980t$467.9415———
Asphalt Concrete PavementItem F982t$475.607———
Supply and Install Sign Panels - Extruded AluminumItem F992m²$521.212low sample———
Galvanic Corrosion Protection - Supply and InstallItem F993anodes$93.236———

STA 0+480The most-tendered items

The contract count is the best guide to how much weight an average can bear. In this group the most-tendered items are:

STA 0+600Biggest year-on-year changes

Among the 8 items in this group with five or more contracts in both 2025 and 2026, these moved most. Annual averages shift with the mix of contracts tendered, so a big move can reflect a few unusual jobs.

Item2025 avg2026 avgChange
Supply of Piling - Plain Steel H-PileItem F812 · per m$189.93$262.86+38%
Pile DrivingItem F818 · per m$45.08$61.14+36%
Concrete - Class HPCItem F841 · per m³$3,135$4,133+32%
Deck WaterproofingItem F974 · per m²$133.42$84.68−37%
Heavy Rock Riprap (Class 1)Item F500 · per m³$315.15$292.55−7%
Plain Reinforcing Steel - SupplyItem F850 · per kg$2.90$2.94+1%

STA 0+720Where to go next

Questions people ask

What is in the bridges, structural concrete, piling and riprap group of Alberta's unit price averages?

The 2026 workbook lists 44 items in this group, from Excavation - Structural (item F188) to Galvanic Corrosion Protection - Supply and Install (item F993). Each is the average of the three lowest bids on Alberta provincial highway contracts.

Which bridges & structures item is tendered most often?

Heavy Rock Riprap (Class 1) (item F500) rests on the most contracts in this group, with 38 contracts. Its 2026 average is $292.55 per m³1.

Can I use these prices for a private project?

Only as a benchmark. These are highway-scale averages, and small private jobs usually pay more per unit because mobilization, minimum charges and disposal are spread over less work. Send your scope and quantities on the project brief for a real number.

Sources

  1. Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026