Signs, pavement markings and roadside safety: 2026 unit prices

59 tendered items with their 2026 provincial averages, contract counts and two prior years, taken from Alberta's highway contracts.

Sheet D-507Checked 2026-10-257 min read1 source

59Items in this group with a 2026 provincial average
30Items resting on ten or more contracts
32Contracts behind the most-tendered item, Flexible Guide Post/Delineator - Round - Supply and Install1

STA 0+120What this group covers

A road is not finished until drivers can read it and survive leaving it. This group covers signs and posts, painted and durable pavement markings, milled rumble strips, guardrail and the impact attenuators that soften a crash at a rigid hazard.

It is the largest group by item count and many items are tendered on most highway contracts, so several of its averages rest on twenty or thirty contracts.

The 2026 workbook has 59 items in this group; 30 rest on ten or more contracts. Detailed pages: guardrail, impact attenuators, pavement line painting, milled rumble strips.

STA 0+240How these items are priced

Items are paid per sign, per post, per kilometre of line, per metre of guardrail or per unit, depending on what is being counted. Line painting is priced per kilometre of roadway rather than per metre of paint, so the price reflects the number and type of lines at that location.

STA 0+360Every item, with 2025 and 2024 averages

Each row is the average of the three lowest bids on contracts tendered May 1, 2025 to June 24, 2026. Rows marked low sample rest on fewer than three contracts.

Alberta provincial highway tenders: average unit prices1
ItemUnit2026 avgContracts2025 avg2024 avgvs 2025
Remove and Dispose of Existing Signs - One PostItem S205sign$500.871low sample———
Remove and Dispose of Existing Signs - Two PostItem S210sign$5,2441low sample———
Construction Advisory SignItem S241sign$3,81724———
Concrete Base - Supply and InstallItem S261bases$1,43613———
Supply of Signs, 3/4" PlywoodItem S270m²$221.5011———
Supply of Signs, Extruded AluminumItem S271m²$350.4014———
Supply of Signs, AluminumItem S272m²$198.4527———
Supply of Signs, Aluminum - Reflective Sheeting for Specialized ApplicationsItem S273m²$250.1824———
Removal and Reinstallation or Disposal of Existing Signs - One PostItem S275sign$120.0227———
Removal and Reinstallation or Disposal of Existing Signs - Two PostsItem S277sign$324.9920———
Concrete Base - Remove and DisposeItem S284bases$479.2811———
Install Sign - Less than 1 m2Item S288sign$64.6028———
Install Sign - 1 m2 to 3 m2Item S289sign$161.0019———
Install Sign - over 3 m2Item S290sign$813.7813———
Remove and Reinstall Breakaway Steel PostsItem S291post$338.952low sample———
Remove and Dispose - Breakaway Steel PostsItem S292post$173.9810———
Painted Pavement Message - Gore AreaItem S309message$1,6198———
Painted Pavement Message - Turn Arrow (Single or Double)Item S310message$205.153———
Painted Pavement Message - Stop BarItem S315message$240.852low sample———
Painted Pavement Message - Stop AheadItem S320message$382.272low sample———
Painted Pavement Message - STOPItem S321message$238.562low sample———
Painted Pavement Message - Railway CrossingItem S326message$506.272low sample———
Painted Pavement Message - Pedestrian CrossingItem S327message$373.331low sample———
Removal of Existing Painted Pavement MessageItem S329message$545.301low sample———
Durable Pavement Message - Turn or Straight Arrows (Single or Double)Item S341message$337.1724———
Durable Pavement Message - Stop BarItem S342message$620.3625———
Durable Pavement Message - Railway CrossingItem S343message$928.005———
Durable Pavement Message - Stop AheadItem S344message$983.7612———
Durable Pavement Message - Pedestrian CrossingItem S346message$806.973———
Durable Pavement Message - STOPItem S347message$635.8512———
Removal of Existing Durable Pavement MessageItem S349message$296.002low sample———
Roadway Lines - Supplying Paint and Painting (Directional Dividing and 2 Edge Lines)Item S350km$1,11929$1,15732 contracts$1,11528 contracts−3%
Roadway Lines - Supplying Paint and Painting (Lane Dividing and 2 Edge Lines)Item S351km$1,16023———
Roadway Lines - Supplying Paint and Painting (Lane Dividing Lines)Item S352km$317.3913———
Roadway Lines - Supplying Paint and Painting (Directional Dividing and 1 Edge Line)Item S355km$425.565———
Roadway Lines - Supplying Paint and PaintingItem S356km$460.735———
Intersection Lines - Supplying Paint and PaintingItem S360intersection$467.8829———
Interchange Lines - Supplying Paint and PaintingItem S370interchange$2,8805———
Removal of Existing Painted LinesItem S375m$5.373———
Removal of Existing Roadway LinesItem S376km$8,1782low sample———
Underground Electrical Conduit - Supply and Install - Trench ExcavationItem S400m$69.877———
Underground Electrical Conduit - Supply and Install - Pushed ConduitItem S405m$149.0311———
Milled Rumble Strips for Stop ConditionsItem S700set$3,0119———
Milled Rumble Strip - ShoulderItem S706km$2,47124$1,97525 contracts$1,19418 contracts+25%
Milled Rumble Strip - CentrelineItem S707km$2,42218———
Supply and Install Breakaway Steel Posts - W150 x 14Item S730post$997.969———
Supply and Install Breakaway Steel Posts - W200 x 15Item S735post$1,1114———
Supply and Install Breakaway Steel Posts - W150 x 22Item S740post$1,5348———
Supply and Install Breakaway Steel Posts - W200 x 27Item S745post$1,5252low sample———
Supply and Install Post - 100mm x 150mmItem S755post$571.962low sample———
Cluster Frames - Supply and InstallItem S765frame$283.9810———
Supply and Install Post (100 mm x 150 mm)Item S772post$228.0926———
Removal and Reinstallation or Disposal of Existing SignsItem S775sign$105.001low sample———
Strong Post W-Beam Guardrail - Supply and InstallItem S805m$169.3623$144.6525 contracts$133.4624 contracts+17%
Thrie Beam Guardrail - Supply and InstallItem S806m$1,2441low sample———
Impact Attenuator (NCHRP 350/MASH 2009 TL-3) - Supply and InstallItem S811unit$6,13920$5,18526 contracts$5,15723 contracts+18%
Remove, Salvage and Reinstall Existing GuardrailItem S820m$100.753———
Remove and Dispose of Existing GuardrailItem S825m$25.1919$17.9025 contracts$24.5832 contracts+41%
Flexible Guide Post/Delineator - Round - Supply and InstallItem S830post$68.8732———

STA 0+480The most-tendered items

The contract count is the best guide to how much weight an average can bear. In this group the most-tendered items are:

STA 0+600Biggest year-on-year changes

Among the 5 items in this group with five or more contracts in both 2025 and 2026, these moved most. Annual averages shift with the mix of contracts tendered, so a big move can reflect a few unusual jobs.

Item2025 avg2026 avgChange
Remove and Dispose of Existing GuardrailItem S825 · per m$17.90$25.19+41%
Milled Rumble Strip - ShoulderItem S706 · per km$1,975$2,471+25%
Impact Attenuator (NCHRP 350/MASH 2009 TL-3) - Supply and InstallItem S811 · per unit$5,185$6,139+18%
Roadway Lines - Supplying Paint and Painting (Directional Dividing and 2 Edge Lines)Item S350 · per km$1,157$1,119−3%
Strong Post W-Beam Guardrail - Supply and InstallItem S805 · per m$144.65$169.36+17%

STA 0+720Where to go next

Questions people ask

What is in the signs, pavement markings and roadside safety group of Alberta's unit price averages?

The 2026 workbook lists 59 items in this group, from Remove and Dispose of Existing Signs - One Post (item S205) to Flexible Guide Post/Delineator - Round - Supply and Install (item S830). Each is the average of the three lowest bids on Alberta provincial highway contracts.

Which signs, markings & safety item is tendered most often?

Flexible Guide Post/Delineator - Round - Supply and Install (item S830) rests on the most contracts in this group, with 32 contracts. Its 2026 average is $68.87 per post1.

Can I use these prices for a private project?

Only as a benchmark. These are highway-scale averages, and small private jobs usually pay more per unit because mobilization, minimum charges and disposal are spread over less work. Send your scope and quantities on the project brief for a real number.

Sources

  1. Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026