Unit price · Sheet D-619
Guardrail: 2026 Alberta unit price
What Alberta paid for guardrail on provincial highway contracts in 2026, from 23 contracts, and how the average has moved since 2024.
STA 0+120What guardrail covers
Guardrail keeps vehicles from leaving the road onto hazards or steep slopes. The standard item is strong-post W-beam guardrail (S805), priced per metre supplied and installed. Removal and disposal (S825) and salvage and reinstallation (S820) are separate items, and thrie-beam guardrail (S806), a stronger section, is rare in the data.
STA 0+2402026 prices and three-year history
In 2026 the provincial average for Strong Post W-Beam Guardrail - Supply and Install (item S805) was $169.36 per m1, the average of the three lowest bids on 23 contracts tendered May 1, 2025 to June 24, 2026. That is up 17% on the 2025 average of $144.65 (25 contracts) and up 27% on 2024's $133.46 (24 contracts).
| Item | Unit | 2026 avg | Contracts | 2025 avg | 2024 avg | vs 2025 |
|---|---|---|---|---|---|---|
| Strong Post W-Beam Guardrail - Supply and InstallItem S805 | m | $169.36 | 23 | $144.6525 contracts | $133.4624 contracts | +17% |
| Remove and Dispose of Existing GuardrailItem S825 | m | $25.19 | 19 | $17.9025 contracts | $24.5832 contracts | +41% |
| Remove, Salvage and Reinstall Existing GuardrailItem S820 | m | $100.75 | 3 | — | — | — |
| Thrie Beam Guardrail - Supply and InstallItem S806 | m | $1,244 | 1low sample | — | — | — |
Items marked low sample rest on fewer than three contracts. Treat them as a single data point.
STA 0+360How the price varies across Alberta
Alberta publishes regional averages for some items. For item S805, Southern averaged $205.61 and Peace $154.29, which is 33% higher. Regional gaps like this come from haul distance, local competition and the mix of work tendered in each region.
| Region | Avg per m | Contracts |
|---|---|---|
| Southern region | $205.61 | 4 |
| Central region | $158.41 | 10 |
| North Central region | $173.37 | 6 |
| Peace region | $154.29 | 3 |
| Province | $169.36 | 23 |
STA 0+480What moves the price
Steel prices, post spacing and embedment (rock or frost make driving posts slow), end-treatment design, the length per contract and traffic exposure during installation set the rate. Guardrail location and design follow the road's design speed and roadside hazards, so a metre is not a constant.
STA 0+600Using the number in a budget
These are benchmarks, not quotes. Each figure is the average of the three lowest bids on Alberta provincial highway contracts, at highway quantities. A small private job pays more per unit because mobilization, minimum charges and disposal are spread over less work.
Use the number to sanity-check a unit rate in a bid or to see which way a price has moved, then ask for a quote that matches your quantities, access and timing.
STA 0+720Related prices, guides and tools
Questions people ask
How much does guardrail cost in Alberta?
On Alberta provincial highway tenders in 2026, Strong Post W-Beam Guardrail - Supply and Install (item S805) averaged $169.36 per m1, the average of the three lowest bids across 23 contracts. It is a highway-scale benchmark, not a quote for a particular job.
Has the price of guardrail gone up?
The 2026 average of $169.36 per m is up 17% on the 2025 average of $144.65 and up 27% on 2024's $133.46. Annual averages move with the mix of contracts tendered, so a change in the average is not the same as a change in the cost of the work.
Can I use this price for a small job, or outside Alberta?
Use it as a reference point, not a price. The average reflects highway contracts, so a smaller job usually costs more per unit, and no other province publishes a comparable average for this item. For your own job, send the scope, quantities and location on the project brief and we reply by email.
Why does Alberta list guardrail under several item codes?
Each code is a separate tender item with its own specification, and the workbook gives no description beyond the item name. Cite prices by code, and read the contract documents to see what each code includes.
Sources
- Unit Price Averages (workbook updated 2026-06-24)Alberta Transportation and Economic Corridors · 2026