Guide · Sheet G-407
What is a bid bond?
A bond is a promise from a third party, the surety, that stands behind a contractor’s promise to the owner. Most public civil tenders ask for one before a contractor can even submit a price.
A bond is a three-party arrangement: the contractor (the principal), the owner (the obligee), and a surety company that puts its own financial strength behind the contractor's promise. If the contractor fails to do what it promised, the surety steps in, up to the bonded amount, rather than the owner being left to chase an underfunded contractor through the courts alone. Public civil tenders in Canada routinely require one or more bonds before a bid is even considered.
STA 0+120What a bid bond actually covers
A bid bond is submitted with the bid itself, not after award. It puts the surety on the hook for a stated amount, or a percentage of the bid price, if the contractor wins the tender and then refuses to sign the contract or fails to provide the performance and payment bonds the tender requires. It does not cover the quality of the finished work or a contractor's performance during construction — it exists purely to keep bidders honest about their intent to actually take the job if they win it. An owner who is left without a signed contract because the low bidder walked away can draw on the bid bond to cover the cost of re-tendering or accepting the next-lowest bid.
STA 0+240Bid bond, performance bond and payment bond
| Bond | Submitted | Covers |
|---|---|---|
| Bid bond | With the tender submission | The risk that the winning bidder refuses to sign the contract or provide the required bonds |
| Performance bond | At contract award | The owner's cost to complete the work if the contractor defaults during construction |
| Labour and material payment bond | At contract award | Unpaid subcontractors and suppliers on the job if the contractor fails to pay them |
The performance bond and the payment bond are usually issued together, often each set at 50% or 100% of the contract price depending on the owner's requirement, and both typically run for the length of the contract plus a warranty period. A bid bond's job ends the moment the contract is signed and the other two bonds are in place; it does not carry through construction.
STA 0+360Bid bond vs agreement to bond
Some tenders accept an agreement to bond (sometimes called a consent of surety) instead of a fully executed bid bond. It is a letter from the surety confirming it is prepared to issue the performance and payment bonds for that specific project up to a stated penal sum, if the contractor is awarded the work. It signals the same thing a bid bond does — that a surety has assessed the contractor and is prepared to stand behind it — without the paperwork of a full bond at the bid stage. Read the tender document carefully: some owners accept either instrument, and some ask for both a bid bond and a separate agreement to bond covering the performance and payment bonds to come.
STA 0+480What determines how much bonding a contractor can get
A surety is not pricing risk on a single job in isolation; it is underwriting the contractor as a business. The factors that move a surety's decision are broadly consistent across the industry: financial statements and working capital, the contractor's current work-in-progress schedule (how much bonded work is already outstanding), bank references, the experience and stability of the management team, and the contractor's claims and completion history. A contractor with strong financials but a thin track record on projects this size, or one that is already carrying a large volume of bonded work relative to its capital, may find its bonding capacity is the limiting factor on how large a tender it can bid — well before price becomes the issue. Building a relationship with a surety broker before a large tender closes, not during bid week, is what actually expands that capacity over time.
Bonding capacity is usually expressed two ways: a single-project limit (the largest job the surety will bond at once) and an aggregate limit (the total value of bonded work the contractor can carry across every active project combined). A contractor can be well within its single-project limit and still be unable to bond a new job because its aggregate limit is tied up in other work that has not finished and released its bonds yet. Tracking both numbers, not just the size of the job in front of you, is part of deciding whether to bid at all.
STA 0+600How bonding compares to a statutory holdback
A bond and a statutory holdback solve different problems and are not substitutes for each other. A bond is a third party's promise, triggered only if the contractor fails to perform or pay; a holdback is money the owner (or a contractor further up the chain) is required by law to retain from every payment, regardless of whether anything has gone wrong. Alberta's statutory holdback, for example, is a flat 10% withheld from every payment until lien rights expire1, running in parallel with whatever bonding the tender required. See construction holdbacks for the rate and release timing in each province, and prompt payment and adjudication for how the rest of an invoice is supposed to get paid on time.
STA 0+720When a tender asks for a bond
Bonding is close to universal on Canadian public civil tenders of any real size, and the requirement is stated directly in the tender document, usually as a percentage of the bid price for the bid bond and a percentage of the contract price for the performance and payment bonds. See bidding on public tenders for where those tenders are posted and how they get evaluated. A tender that skips a bonding requirement is more the exception than the rule once the contract value moves past a small local job, because the owner is otherwise carrying the entire risk of a contractor default with no third party standing behind it. A private owner may waive bonding for a smaller job, but even then, a bonded contractor is often able to demonstrate a level of financial standing an unbonded one cannot, simply because a surety already underwrote it.
Financial information, not a placement recommendation
Bonding capacity, premium and terms are underwritten individually by each surety. This page explains how the mechanism works; talk to a licensed surety broker about a specific contractor's bonding program.
Questions people ask
What does a bid bond cover?
It covers the owner’s cost if the winning bidder refuses to sign the contract or provide the required performance and payment bonds. It does not cover the quality of the finished work.
What is the difference between a bid bond and a performance bond?
A bid bond is submitted with the tender and expires once the contract is signed. A performance bond is issued at award and covers the owner’s cost to complete the work if the contractor defaults during construction.
What is an agreement to bond?
A letter from a surety confirming it will issue the performance and payment bonds for a specific project if the contractor is awarded the work, submitted in place of, or alongside, a full bid bond.
Is a bid bond the same as a holdback?
No. A bond is a surety’s promise triggered only by a contractor default; a holdback is money withheld from every payment by law, such as Alberta’s 10% statutory holdback1, regardless of whether anything has gone wrong. See construction holdbacks.
What determines how much bonding a contractor can get?
Mainly financial strength and working capital, current work-in-progress relative to capital, bank references, management experience and claims history — a surety underwrites the contractor as a business, not just the one project being bid.
Can a contractor bid without a bid bond if the tender requires one?
No. A bid missing a required bid bond, or an accepted agreement to bond, is normally disqualified as non-compliant regardless of price, the same way a missing mandatory form would be. See bidding on public tenders for the other pieces a compliant bid needs.
Sources
- Prompt Payment and Construction Lien Act, RSA 2000, c P-26.4 (office consolidation current as of April 1, 2025)Alberta King's Printer · consolidation current as of 2025-04-01
- Ontario Highways Program Update, ORBA, April 24, 2025Ontario Ministry of Transportation · fiscal 2024-25
Related
-
G-401
Call before you dig
One-call centres by province, notice periods, what the paint means and what to do when marks are missing.
-
G-402
Trench safety & shoring
How deep you can dig without protection in every province, and the sloping, shoring and box rules.
-
G-403
Spring road bans
Why thaw closes roads to heavy loads, how Alberta, Saskatchewan, Manitoba and Ontario set them, and how to plan around them.